Notified maximum demand (NMD) on an Eskom supply
What is NMD on an Eskom supply, how do you reduce it, and what happens if you go over it?
Eskom's schedule defines NMD as the contracted maximum demand, notified in writing by the customer and accepted by Eskom per point of supply. Demand is measured as the highest average in kVA over a 30-minute integrating period in the billing month.
The rules for notifying, changing and exceeding NMD are approved by NERSA and published as the NMD and MEC rules.
Monthly utilised capacity is the higher of the NMD and the highest half-hour demand measured in the month.
Annual utilised capacity is the higher of the NMD and the highest monthly figure above a 5% band over the NMD, across a rolling 12 months that includes the current month. On many tariffs, network capacity charges are billed on the annual utilised capacity.
The rules count each month the NMD is exceeded as an event over a rolling 12 months. The first two events, or any two events within 5% of the NMD, are treated differently from later ones. From the third event above the 5% band, the annual utilised capacity is reset to the higher recorded demand and does not fall again within the 12 months.
An excess network capacity charge then applies to the kVA above the NMD, at the tariff's network capacity rate. The NMD itself does not change unless the customer applies in writing.
An increase follows the utility's normal connection process and may need network work and a connection charge. Temporary increases can be agreed in advance for short-term needs such as commissioning a plant, not for seasonal or repeating demand.
A reduction needs 12 months' written notice, or at least three months where a valid reason is given. A reduction below the highest demand measured in the last 12 billing periods is refused unless it is motivated, for example by a change in operations, load management equipment or demand-side measures. If a reduced NMD is exceeded beyond the 5% band within the following 12 months, the reduction can be reversed and the account rebilled with interest.
Lowering the NMD is a written application to the utility for each point of supply. Under the NERSA-approved rules it needs 12 months' notice, or at least three months where the utility accepts a valid reason.
Before applying, read the highest half-hour demand in kVA for each of the last 12 billing periods from the bills or meter data. A requested NMD below that highest figure is refused unless the application is motivated, for example by a change in operations, installed load management equipment or demand-side measures.
After a reduction, the new NMD is tested by the same rules: if demand goes beyond the 5% band over it within the following 12 months, the reduction can be reversed and the account rebilled with interest. A request is therefore supported by measured demand, not an estimate.
Customers supplied by a municipality are on that municipality's own tariff, approved by NERSA each year. Its names, periods and rules can differ from Eskom's, so read the municipality's published tariff schedule.
Questions
For loads, Eskom's rules express NMD and utilised capacity in kVA.
Twelve months' written notice, or at least three months with a valid motivation the utility accepts.
Apply in writing for each point of supply. The request should be at or above the highest half-hour demand measured in the last 12 billing periods, or be motivated by a change in operations, load management equipment or demand-side measures.
Yes. If the reduced NMD is exceeded beyond the 5% band within the following 12 months, the reduction can be reversed and the account rebilled with interest.
Not necessarily. A municipality applies its own NERSA-approved tariff and rules, so read its published tariff schedule.