Choosing an electricity tariff

How do Eskom's main business tariffs differ?

A time-of-use tariff charges different energy rates in peak, standard and off-peak periods, and in the high- and low-demand seasons. A site that can move load out of peak periods sees that reflected in the energy charge. A site that cannot may see the opposite.

Megaflex: time-of-use, for urban customers with an NMD greater than 1 MVA.

Miniflex: time-of-use, for urban customers with an NMD from 16 kVA up to 5 MVA.

Nightsave Urban: for high load factor urban customers with an NMD from 25 kVA and no grid-tied generation.

Businessrate: for commercial and similar supplies in urban areas with an NMD of up to 100 kVA and no grid-tied generation.

Ruraflex: time-of-use, for rural customers with an NMD from 16 kVA at the supply voltages the schedule sets.

On Megaflex, part of the network charge is a demand charge in R/kVA on the highest demand during peak and standard periods. On Miniflex, the equivalent network demand charge is in c/kWh on energy used in those periods. Reactive energy is measured per half-hour on Megaflex and on billing-period totals on Miniflex.

Since April 2025, energy charges on most tariffs have been split into separate parts, including a generation capacity charge in R/kVA and a legacy charge in c/kWh.

Compare at least 12 months of half-hourly readings against each eligible tariff's structure at the rates in force. Read the electricity supply agreement for notice periods and conditions. The utility decides eligibility.

Customers supplied by a municipality are on that municipality's own tariff, approved by NERSA each year. Its names, periods and rules can differ from Eskom's, so read the municipality's published tariff schedule.

Questions

No. Rates change each year; read them in the current Eskom schedule of standard prices.

The schedule describes both as for supplies without grid-tied generation.